High-Low method is one of the several techniques used to
split a mixed cost into its fixed and variable components (see cost
classifications). Although easy to understand, high low method
is relatively unreliable. This is because it only takes two extreme activity
levels (i.e. labor hours, machine hours, etc.) from a set of actual data of
various activity levels and their corresponding total cost figures. These
figures are then used to calculate the approximate variable cost per unit (b)
and total fixed cost (a) to obtain a cost volume formula:
y
= a + bx
|
High-Low
Method Formulas
Variable
Cost per Unit
Variable cost per unit (b) is calculated using the
following formula:
Variable
Cost per Unit =
|
y2 − y1
|
x2 − x1
|
Where,
y2 is the total cost at highest level of activity;
y1 is the total cost at lowest level of activity;
x2 are the number of units/labor hours etc. at highest level of activity; and
x1 are the number of units/labor hours etc. at lowest level of activity
y2 is the total cost at highest level of activity;
y1 is the total cost at lowest level of activity;
x2 are the number of units/labor hours etc. at highest level of activity; and
x1 are the number of units/labor hours etc. at lowest level of activity
The variable cost per
unit is equal to the slope of the cost volume line (i.e. change in total cost ÷
change in number of units produced).
Total
Fixed Cost
Total fixed cost (a) is calculated by subtracting total
variable cost from total cost, thus:
Total
Fixed Cost = y2 − bx2 = y1 −
bx1
|
Example
Company α wants to determine the cost-volume relation between
its factory overhead cost and number of units produced. Use the high-low method
to split its factory overhead (FOH) costs into fixed and variable components
and create a cost volume formula. The volume and the
corresponding total cost information of the factory for past eight months are
given below:
Month
|
Units
|
FOH
|
1
|
1,520
|
Rs.36,375
|
2
|
1,250
|
38,000
|
3
|
1,750
|
41,750
|
4
|
1,600
|
42,360
|
5
|
2,350
|
55,080
|
6
|
2,100
|
48,100
|
7
|
3,000
|
59,000
|
8
|
2,750
|
56,800
|
Solution:
We have,
at highest activity: x2 = 3,000; y2 = Rs.59,000
at lowest activity: x1 = 1,250; y1 = Rs.38,000
at highest activity: x2 = 3,000; y2 = Rs.59,000
at lowest activity: x1 = 1,250; y1 = Rs.38,000
Variable Cost per Unit = (Rs.59,000 − Rs.38,000) ÷ (3,000 −
1,250) = Rs.12 per unit
Total Fixed Cost = Rs.59,000 − (Rs.12 × 3,000) = Rs.38,000 − (Rs.12 × 1,250) = Rs.23,000
Cost Volume Formula: y = Rs.23,000 + 12x
Total Fixed Cost = Rs.59,000 − (Rs.12 × 3,000) = Rs.38,000 − (Rs.12 × 1,250) = Rs.23,000
Cost Volume Formula: y = Rs.23,000 + 12x
Due to its unreliability,
high low method is rarely used. The other techniques of variable and fixed cost
estimation are scatter-graph method and least-squares regression method.
No comments:
Post a Comment